3.12 Centering release
For centering releasing
notes, refer to chapter six and eight of current report. Centering is
anyhow a temporary structure of which General Engineering may be not
considered responsible either for what concern the design of it, either
for what concern assembling, disassembling, adjusting and management.
3.13 Drainage, piping and waterproofing
Reference: |
BoQ |
3.3.12.0 |
Drw |
RE-08 |
For what concern drainage
systems it has been followed the ancient methods with some additional
devices that may improve things and allow preservation, durability and
avoid any future damage to the structure:
surface
rain waters drainage:
Waters are collected in
rain wells located at the extremes lower levels of the pavement: each area
has its well and, over the bridge pavement, very small interventions will
be carried out next to the borders. Moreover, underneath stone thresholds,
at the bridge pavement limits, slots have been foreseen to drain water out
towards bigger wells. Existing drain water hole by the south west side has
been maintained. Bridge pavement rows, as originally conceived should help
water to flow away.
rain water
piping:
Wells will be connected one
to each other and towards the river by underground piping. Rain water
outlets (r.w.o.) should be provided at least in double ways: in case of
obstructions no large puddles will take place and maintenance will not
occur so urgently. External rain water outlets should be placed in
abutment corners, (as previously located), and external pipes should be
made of oxidise copper (when colour gets dark and opaque). At the bottom
of vertical piping inspection wells are required. Next to the abutment
walls when r.w.o. come out, stone spouts are required.
bridge
pavement waterproffing:
The ancient type of
waterproofing may be repeated: bridge stone flooring should be placed on a
mortar layer with waterproofing requisites; connection joints of the
pavement should be accurately sealed. Mortar type should be defined and
approved by laboratory tests, and may be used only if it is proved that
this type of device is efficient and water resistant even during time.
Other devices should be worked out if the above is not confirmed.
adjacent
pavement waterproofing:
Same technological systems
may be applied as the above.
abutment
walls top ground areas:
Same technological systems
may be applied as the above, but with additional outlet channels to take
water away towards the river. Mortar layer may be applied only under areas
protected by Tenelija stone blocks or small natural conglomerate rocks,
remaining portions characterised by stable rock areas will be left
unchanged.
inner
bridge lightening voids drainage system:
No water is supposed to get
in the bridge lightening voids, but in case of any infiltration or any
condense phenomena, a waterproofing mortar layer is foreseen on the bottom
of the voids to protect the load bearing arch. Water trap drainage
channels (one per void) are foreseen. Underground channels should be long
enough to reach a ground layer with high permeability (according to CONEX
investigations), and channels should be filled with rubble of grain size
which gets larger to the bottom.
3.14 Finishing works
Reference: |
BoQ |
3.3.13.0 |
Drw |
XXXX |
For what concern the
finishing works on stones refer to §7.11 of this report. The model, that
the Company in charge of the rehabilitation works is requested to assemble
in real scale, should be taken as a reference during the finishing works,
being the one that has been approved by the ICE.
Anyhow foreseen finishing
works are here next resumed and listed:
Finishing
works on the stones:
Finishing for the stone is
aimed at reproducing the same type of worked surface as the one of the
ancient bridge for the different elements. Moreover finishing works on the
stones is an additional stone work aimed at reducing some ordinary
construction imperfections in the assembling which is judged, (by works
Supervisor), to exceed the average level that characterised the former
bridge. Most probably this work will be needed for the bridge intrados
vault.
Jutting out stone edges
should be smoothed, (as defined in the approved model). Parapets will be
the elements that will mostly require a masterpiece of stone cut and stone
finishing.
Pavement
stone carvings:
Bridge flooring was
probably originally built with no carvings on the stone tiles, and (as Mr.
Bessac has noted), these carvings may have been performed later on: like
from 50 to 200 years later, when stone got slippery. In the rehabilitation
works of the bridge, these carvings will be performed again as they were,
without waiting for the flooring to get slippery: this because the
objective of the current work is to rehabilitate the monument as it was
right before destruction, (a declared scientific copy of the former
bridge), and is not to live again the experience of building a similar
bridge with same techniques and same construction materials. Refer to
drawings RE-01 and SC-09.
Sealing of
joints:
All the bridge joints will
have to be sealed, including pavement joints and elevation joints in order
that no infiltration gets in the bridge inner structure due to rain water
or to floods.
Patina:
Specification of this work stage is given by stone
experts: anyhow "patina" will be a light layer of biologic
material that will be sprayed over the stone surface to avoid any
unpleasant effect during the first months of life of the structure, being
in high contrast to the adjacent historical portions.
3.15 New intervention marks
Reference: |
BoQ |
3.3.14.0 |
Drw |
RE-09 |
In order to declare which
are the new interventions a plan has been worked out. The plan may be
subdivided in two different sections: declaration of the joint in the
pavement trough the use of metal marks and marking of some stones, (trough
small and light carvings), in the elevations.
Metal marks
Joint among new
interventions and ancient pavement will be of a double size, (compared to
the other joints of the pavement), and metal marks will be applied. Of
course the shape of the joint line will vary depending on portions of the
former pavement that will be possible to maintain: limit line, in
drawings, is therefore indicative. Metal marks will be applied along the
connection joint on the corners or every cm 30-40. Shape and dimensions of
the joint will be decided trough on site checks by the ICE, as well as any
writings on the mark top cap (like date of works).
Carved
marks
New stones of the
elevation, (like spandrels stones and cornices), which are adjacent to the
ancient ones will be marked with a small and light carving which will be
visible only to a very close observation. Shape and dimensions of the
carved mark will be decided trough on site checks by the ICE, as well as
the type of the carving. In the drawing the carving is symbolically
represented and the code SMS-Bmk means: Stari Most Stones – Bridge
stones – marked ones. Dotted stones, in the drawing, are the stones of
the former bridge, that it has been possible to remount in the original
position depending on their state of conservation (drawing shows an
hypothetical configuration).
3.16 Bridge pavement remedial works
Reference: |
BoQ |
3.2.8.0 – 3.3.10.0 |
Drw |
DS-01; RM-01; RE-01;
SC-09 |
Additional explanations
should be given for what concern the bridge pavement over the abutment
walls: in this design, even those portions which prosecute inwards over
the abutments, and until the limits of the intervention area, have been
called "bridge pavement", being conceived as a walk path made of
same construction materials and mounted with an identical layout. Of
course these additional floorings, being still on-site and not destroyed,
are foreseen to be repaired. The current condition of floorings is quite
ruined: some spots have been subsided and some stone elements are damaged
or lacking.
For what concern
preliminary cleaning, dismantling and demolition works refer to §3.6.3
and §3.6.7 of this report. Remedial works are, instead, here next
resumed:
Bridge
pavement remounting:
Areas in which pavement has
been dismantled, (with detailed survey and classification), due to the
bridge and abutment fill removal and strengthening. These portions of
flooring should be carefully remounted in the original locations and
respecting former layout.
Bridge
pavement lacks repair:
Areas that were covered
with reinforced concrete blocks and plinths, that have been demolished and
that should be repaired and integrated with new pavement stones of same
type and layout of the original ones.
Bridge
pavement remedial works:
Single damaged stones of
pavement that should be repaired or substituted with new ones of same type
of the adjacent ones respecting the original layout. These damaged stones
are sometimes in isolated locations, (quantification is by estimation),
and some others are in drawn areas, (refer to drawing RM-01). Remedial
works should preserve or repair mortar layer underneath.
In any case remedial works
of the pavement should preserve and repair the ancient "terra
rossa" and mortar layers of protection and waterproofing which are
located underneath the stone flooring, (in case they are reached during
dismantling works). Continuity of the layers is required to avoid rain
water infiltration in the abutment. Bridge pavement is composed by stone
rows and stone tiles; layout of them may be worked out from design
drawings and not randomly performed, since, as it has been conceived,
should help rain water to flow away. Tiles and rows should be assembled
carefully on a flat and homogeneous preparation layer making connections
as much close as possible and sealing them to avoid rain water
infiltration. Pavement row stones should be bevelled and shaped as the
ancient ones in order to make the walk easier to the users.
Areas in which the pavement
is slightly subsided may be left as they are, being the signs of time part
of the beauty of this original portions. While, for what concern the areas
of the flooring that will be remounted, (junction zone between ancient and
new pavement), it has to be noted that in those spots the height of
parapets were particularly low, so that even with the fences it may
results, nowadays, unsafe, (related to current security norms); therefore
a slight adjusting of the height of the remounted pavement, (by lowering
it), would be advisable. In design drawings this intervention hasn't been
proposed since it will have to be evaluated by the works Supervisor
on-site.
In design drawings, dashed
lines next to doorsteps and access of other buildings mean that works have
to be co-ordinated with the design for the Towers and adjacent buildings
since in some spots stairs may be reconstructed. Flooring has been
quantified anyway.
Dismantled krecnjak stone
socles, (east side), between bridge pavement and adjacent flooring should
be, remounted in the original locations, (elements that are not damaged).
Other elements which are lacking should be replaced and integrated with
new quarried ones with similar shape, finishing layout and colour to the
adjacent ones. Refer to drawing RM-01 and SC-09.
3.17
Adjacent areas works
Reference: |
BoQ |
5.0.0.0 |
Drw |
DS-01; RM-01; RE-01;
SC-09 |
Other spots that are
involved in this design work, (and included in site limits), have been
defined as "adjacent areas" and may be subdivided as follows:
- areas adjacent to bridge pavement
(located on the east side)
- areas over the abutment walls (located
either on east and west side)
In the above mentioned
zones only small protection and preservation interventions are foreseen.
Anyhow some cleaning, dismantling and demolition is required before repair
works could take place.
3.17.1 Adjacent areas: dismantling works
Reference: |
BoQ |
5.1.0.0 |
Drw |
DS-01 |
Dismantling works are here
next resumed:
Demolition
of concrete blocks:
Existing concrete blocks
should be demolished; those which are over the pavement should be
demolished before pavement remedial works; the others may be demolished at
the end of the works once they are not necessary for any provisional work.
Demolishing of reinforced concrete blocks should be performed with no
vibration and taking care for the adjacent unstable structures.
Underground thickness of the blocks has been estimated and quantified.
Demolition of underground portions may be not performed if there is any
structural risk: to be decided on the Supervisor responsibility.
Demolition
of masonry walls:
Masonry walls that are
almost completely ruined should be partially demolished until a good layer
is found. There is only one case of demolition of a small masonry wall
that is almost completely ruined: it is located at the borders of the
works limit by the north-east side (drawing DS-01 position E-10). It
should be partially demolished until a good layer is found.
Rubble
removal and cleaning:
Portions of the pavement
which are covered by rubbles should be cleaned before flooring remedial
works.
Dismantling
of damaged elements over the abutment walls:
Dismantling of damaged
elements, either pavement blocks, either natural small conglomerate rocks
which are not anchored to the soil; cleaning and preparation of the area
for the remedial works.
3.17.2 Adjacent areas: remedial works
Reference: |
BoQ |
5.2.0.0 |
Drw |
RM-01; RE-01; SC-09 |
Repair works are here next
resumed:
Adjacent
pavement remedial works:
Portions of pavement
adjacent to the bridge flooring will be reintegrated with new stones of
the type of river stones, (small size river pebbles – header layout),
similar to small remaining portions still on site in that spot. This
remedial work will be performed only after dismantling of the reinforced
concrete blocks and plinths which are over the area.
Protection
pavement over the abutment walls:
Pavement in Tenelija blocks
(layout and thickness similar to a masonry wall – equal to still
remaining portions on site in that spot), is a sort of masonry protection
that should be remounted and reinforced with cramps, and should be stuck
to the underneath ground by metal anchor bars. Waterproofing and
protection from infiltration should be performed by mortar layer use and
by accurate sealing of joints.
Waterproofing
and protection over the abutment walls:
Areas adjacent to the
intervention spot should be protected from infiltration of rain water in
order to avoid future damages to the abutment walls. Protection should be
performed following the original traditional devices like the use of a
mortar layer underneath stone blocks or settling natural conglomerate
rocks. Water channels should be fixed in order to take rain water away.
Waterproofing
and protection over the abutment walls (out of work limits):
There are some areas which
should be repaired as the above mentioned ones but in co-ordination with
the yard of the Towers and adjacent buildings, being out of the work
limits. This intervention should be performed during the restoration works
of surrounding buildings.
Masonry
wall reconstruction:
Portion of ruined wall
should be partially repaired and reconstructed. Type of masonry, layout
and appearance should be as it was before. Shape and height is determined
in the reconstruction drawing. There is only one case of a small masonry
wall that is almost completely ruined: it is located at the borders of the
works limit by the north-east side (drawing RM-01 position E-10).
3.18 Rehabilitation of the abutments walls
Reference: |
BoQ |
4.0.0.0 |
Drw |
DS-02-3; RM-02-3 |
As already introduced, (see
§3.4.2), The abutments walls are, at the moment, fractured in different
points and some of the cracks are also wide, like the one on the west bank
– north side, which runs vertically almost along all the abutment.
Moreover on the east bank – north side we have many damages due to the
shootings that have left wide lacks, cracks and have ruined all the
masonry surfaces. The general condition of the south elevation seems to be
better, more compact and not so much deteriorated.
The condition of the
abutment walls prior to the shooting were not bad, and as far as it can be
gathered from the scarcely readable photographic documentation, they were
mostly compact and only the mentioned wide crack, (on the west bank –
north side), was remarkable. But during centuries the abutment walls seem
to have been frequently restored, since they still look like a patchwork
of different kinds of masonry. The repair works that during centuries have
taken place, may have been mostly required by river floods, by drainage
problems and by settlements of the abutments.
The fact that deterioration
is mostly located on the north side, (from where the river flows), and on
the lower portions, (where Tenelija surface is partially ruined), lead to
think that the river has been the cause of non-structural pre-war damages:
Tenelija ashlars are often characterised by non-structural fissures and by
detaching of outer stone layers.
Structural design for the
repairs of the abutment walls is not included in General Engineering
assignment, since it is one of the task of CONEX Company, that has been
performed with the structural design for the foundations works. Therefore
General Engineering has proceeded to the architectural design of the
non-structural repairs (surface repair works).
Anyhow some general advises
for the structural design are given here next; these observations are not
to be considered as constraints or limits for the works and no
responsibility may be attributed to GE for the following notes:
- The abutment walls should be carefully
consolidated since they are part of the structural system that bears
the load coming from the bridge arch. The stability of these walls and
their resistance is important as much as the foundations.
- The abutments stability, any possible
shift of them, and the cause of the current fractures, should be
carefully evaluated (also with a monitoring system).
- It is important to define which are the
cracks and damages due to the shootings and which are the damages that
were present because of other causes.
- Remedial works for cracks have to be
studied accurately relating them to the causes and it should be
investigated if there are any drainage problems that may also have
been increased by the current condition of the abutments that at the
moment are not protected by rain water infiltration. In fact walls
seem to have some local swellings that should be checked.
- Anyhow before the reconstruction phase
of the bridge arch, cracks on the abutment walls, that constitute a
structural risk, have to be repaired with strengthening tie rods or
any other technique which is the less invasive and the more reversible
as possible.
- Mortar injections, for desegregated and
detached masonry portions of the abutment walls, have to be accurately
inquired and adopted only for real and necessary cases: it is
advisable to have an on-site supervision to evaluate exact
quantification of the intervention.
- Injections and structural deep
interventions should be limited, as much as possible, to the real
necessary cases in order to respect the ancient monument.
- Injections should be performed with the
lowest pressures as possible;
- Another matter that has to be analysed
is the eventual small yielding of the abutments due to the bridge
collapse: the load bearing arch of the bridge, when it was still
erected, discharged a thrust on to the abutments but not anymore after
destruction. This has to be investigated although generally not good
results are achieved in resuming released masonry, and the situation,
even if confirmed, might be probably left as it is.
3.18.1 Theoretical approach to the abutment walls repair works
The approach to the
abutment walls restoration is mainly aimed at their preservation and long
lasting by performing the minimum required intervention necessary to avoid
any further deterioration or collapsing. As far as the surface repairs are
concerned, the architectural design foresees remedial works only of those
masonry lacks that are necessary to avoid river and rain water
infiltration in the inner portions of the abutments, and only of those
masonry surfaces which are so heavily damaged that deterioration is most
likely to proceed. In other words, the global appearance of the abutment
walls should remain unchanged and characterised by all the numerous traces
of ageing and by all the traces of war damages that are not endangering
the structure. ICE, during the 5th Commission has confirmed the
will of leaving small damages of the abutment walls still unchanged and
therefore the proposed theoretical approach is most likely to be followed
during the rehabilitation works.
The abutment walls, this
way, will not be renewed with a different, homogenous and polished layout,
but will maintain their roughness and imperfect appearance which is the
beauty and the historical value of a monument that has, during its long
life, undergone to many interventions of maintenance and improving to face
the strength of the river floods.
Current "patchwork
layout" and masonry stratification is undoubtedly not only a value to
be preserved but also a subject that should be studied by archaeological
experts to understand how the bridge, central core of the city, has
developed. The importance of the above mentioned research work has been
confirmed also by the fact that, during the investigation works performed
by CONEX Company, many findings have come to our knowledge, among which,
the most surprising was the huge void in the north east abutment wing and
another masonry wall, round shaped, behind the current abutment wall. It
seems most likely that the north east wing of the abutments have been
protected by additional walls during time, since that side is the more
exposed to the river flows, that coming slightly from north west discharge
their thrusts on that side mostly. But, referring to the aforesaid
findings, we should also think about the ancient location of the wooden
and suspended bridge, (bequeathed by history), that may have been located
not far from that spot and that may have required some stone structures to
be anchored to.
Another matter that should
be stressed, to perform a correct intervention on ancient masonry walls,
is that any new masonry stone that it is placed either to restore the huge
lacks, either to substitute some heavily damaged ashlar, should have a
small carving that may declare this repair work to any future study of
those walls. Marking by carvings is something which can be seen by a very
close observation of the involved stones and not from any of all the view
points in the surroundings. Architectural design foresees the respect of
the declaration of the new interventions either by documentation,
(drawings and reports), either by small signs on-site according to all the
International prescriptions and requisites that are given for this type of
rehabilitation on the World Cultural Heritage monuments.
3.18.2
Dismantling works in the abutment walls
Reference: |
BoQ |
4.2.0.0 |
Drw |
DS-02-3 |
Small dismantling works
have been foreseen for the abutment walls only for those portions in which
masonry is ruined and unstable, cases are here next listed:
- on the top edges and borders of masonry
walls, where a collapsing due to shootings has happened taking off the
higher portions of the abutment (often parapets);
- on the edges and borders of lacks
located inside masonry wall and due to shootings;
- places where single heavily damaged
stones are present;
- places where recent concrete repair
works have been performed;
Dismantling is aimed only
at taking some damaged edge stones away to find a good, compact and
coherent masonry layout from which it could be possible to start the new
masonry repair work. Stone blocks that are not ruined, (but only
detached), may be reused in the original locations during the repair
works.
After dismantling it is
required to remove any rubble and stone powder from the connection
surfaces on which it is foreseen to place the new masonry. Cleaning of the
connection surfaces is important to allow an efficient grip among adjacent
stones.
Vegetation should be
removed either to allow the performing of the remedial works, either to
allow a check of the joints and of the good condition of the whole masonry
structure.
3.18.3
Remedial works of the abutment walls
Reference: |
BoQ |
4.3.0.0 |
Drw |
RM-02-3 |
Repair works are here next
resumed:
Lacks
repair inside masonry layout:
Remedial works aimed at the
reintegration of masonry layout; lacks due to shootings and lacks due to
dismantling works; (layout and type of stone should be homogeneous to the
adjacent masonry).
Lacks
repair next to masonry margins:
Remedial works aimed at the
reintegration of masonry layout; lacks due to shootings and lacks due to
dismantling works; (layout and type of stone should be homogeneous to the
adjacent masonry).
Masonry
parapets remedial works:
Remedial works aimed at the
reintegration of masonry parapets (two front faces: inside and by the
river side); lacks due to shootings and lacks due to dismantling works;
(layout and type of stone should be homogeneous to the adjacent masonry).
Masonry
parapets top cornices (sills):
Remedial works aimed at the
reintegration of masonry parapets top cornices (sills); lacks due to
shootings and lacks due to dismantling works; (layout and type of stone
should be homogeneous to the adjacent cornices: grey Tenelija).
Highly
damaged surface repair:
Remedial works aimed at the
rehabilitation and regeneration of the stone surface; (finishing and
appearance of stone should be homogeneous to the adjacent masonry).
Structural
cracks repair:
Remedial works for
structural cracks (including tie rods applying, joint sealing trough local
dismantling and remounting).
Drilling
holes repair:
Remedial works aimed at
filling up of the investigation drillings and at replacing a stone top cap
equal (for appearance, finishing and type) to the adjacent masonry.
Vegetation:
Masonry portions covered by
vegetation (to be removed as mentioned in previous paragraph).
Joints
cleaning and sealing:
Recent repair works
performed with cement mortar should be removed, joints should be cleaned
and sealed again with proper binding agent.
3.18.4
Masonry lacks repair
description:
In the remedial works lacks
have been subdivided in different groups depending on the location of them
and on the different foreseen work procedures, (which of course have also
a different code in the BoQ). When lacks are located inside masonry
layout, the following methodology may be applied to perform the repair
works. When lacks are located next to masonry margins, notes are similar
to the following ones, but the work is quite easier since the masonry
layout has to be prosecuted and not inserted avoiding accurate
dimensioning to fit in the gaps and avoiding provisional works to protect
higher layers from collapsing. When parapets are lacking, no other notes
are foreseen, except from the fact that two worked faces are required with
additional finishing layout and accurate work. Similar interventions, (to
lacks), should be performed for the repair of the drilling holes, for
which it is required the filling up of the holes and the placement of the
original "stone caps" with accurate sealing making sure that the
stone element is well linked with mortar to the masonry behind.
methodology:
- Climate should be verified before
starting of the works and temperature should be included between +5°
C and +35° C.
- eventual deeper layers of masonry that
are lacking should be replaced;
- masonry lacking layer should be replaced
and its outer side finished as the adjacent portions;
- no void should be left inside, and
masonry should be compact and well linked;
- connection joints should be preliminary
washed and carefully cleaned;
- joints with adjacent masonry should be
carefully connected and linked with a mortar layer;
- binding agent for mortar has to be
defined by laboratory tests, (as all the construction materials), but
it is suggested the use of a mortar with no mass reducing, (after
maturing time), or an expanding one to allow a compact masonry
reintegration.
- when there is an ashlar layout, cramps
should be fixed following same construction methodology of the
adjacent stones (as described for the spandrel walls of the bridge);
- during execution of works, provisional
devices are required to avoid the collapsing of the above masonry
portions;
- special care is required to make the
ashlars and the masonry stones of the right dimensions to fit exactly
in the lacking portions;
- no stone fragment or small piece should
be used to fit stones in the gaps: stones should be cut properly and
they should be placed on-site with no staggering;
- Stones should be hand worked and
finishing should be hand-made;
- after new masonry portions have been
completed, thickness of joints should be cleaned and accurately sealed
with mortar as defined by laboratory tests;
- it is requested that final appearance of
masonry layout is alike to the adjacent one even for what concern
joint thickness and mortar colour.
materials
to be used and quantification:
Materials to be used for
the intervention should be worked out trough laboratory tests in order to
determine the proper chemical contents and proportions depending on the
stones, (Tenelija or natural conglomerate), on the mortars originally
used, and on the technical requirements that are foreseen for the work.
The worked out products to be used should be tested on small portions
before the work is performed extensively on the damaged areas. Approval of
tests should wait the time necessary for the products to be matured, and
will depend on final result, appearance, colour, grains and efficiency.
Quantification and
proportions of the products used may be subjected to on-site modifications
depending on test results.
3.18.5 Remedial works for the masonry joints
description:
Current condition of
masonry joints is quite heterogeneous, and should be carefully checked to
guarantee a long lasting and durability of the abutments, and to allow the
injecting procedure wherever it will be foreseen due to structural design
requirements according to CONEX Company.
When ancient mortar is
lacking or is heavily desegregated, it should be removed and reintegrated
with proper mortar layer. Mortar layer should be slightly inset, (few
millimetres), compared to the outer masonry layer, in order to distinguish
the new interventions.
methodology:
- Climate should be verified before
starting of the works and temperature should be included between +5°
C and +35° C; special additional cares should be put in cases of
surfaces directly exposed to sun with high temperature and wind and
dry atmosphere;
- joints which have been recently repaired
with cement mortar or with any other device, not suitable with the
traditional constructive techniques, should be cleaned;
- open joints, where mortar has been
washed away due to ageing, should be cleaned from stone powder and
from mortar remnants;
- aforesaid joints should be washed and
carefully sealed with mortar (of the type that will be defined by
laboratory tests): mortar should have same colour and grain appearance
of adjacent masonry;
- Application of the mortar layer should
be performed with small spatulas, (stopping knives), if necessary in
subsequent layers.
- The intervention should not involve the
masonry surface that should be protected or immediately cleaned with a
natural sponge and deionized water.
- As soon as the intervention is
completed, the area should be protected from rain water with water
repellent treatment (see next paragraphs).
materials
to be used and quantification:
Materials to be used for
the intervention should be worked out trough laboratory tests in order to
determine the proper chemical contents and proportions depending on the
stones, (Tenelija or natural conglomerate), on the mortars originally
used, and on the technical requirements that are foreseen for the work.
The worked out products to be used should be tested on small portions
before the work is performed extensively on the damaged areas. Approval of
tests should wait the time necessary for the products to be matured, and
will depend on final result, appearance, colour, grains and efficiency.
Quantification and
proportions of the products used may be subjected to on-site modifications
depending on test results.
3.18.6
Remedial works for stone fissures sealing
description:
Fissures that are
non-structural and that are absolutely "static", (not developing
by getting larger or smaller), should be sealed if they are deep and they
reach stone inner portions or stone core to avoid further deep
deterioration. Maintenance and control of the other fissures is required
during time to perform additional interventions that may be necessary due
to unforeseen development of deterioration. Sealing layer should be
slightly inset, (few millimetres), compared to the outer masonry layer, in
order to distinguish the new interventions.
methodology:
- Climate should be verified before
starting of the works and temperature should be included between +5°
C and +35° C.
- any non-structural fissure which may be
cause of infiltration, and which is located next to the areas were
injections are foreseen should be sealed to avoid the flowing out of
the injecting mass;
- small surface fissures that do not
prosecute in the inner core of the stone Tenelija blocks may be left
as they are with no further repair work;
- sealing should be performed by overflow
or by injection;
- edges of fissures should be preliminary
wetted;
- sealing material should be inserted as
much deep as possible in the fissure;
- the intervention should not involve the
masonry surface that should be protected or immediately cleaned with a
natural sponge and deionized water;
- edges of fissures should be cleaned
after intervention with natural sponge wetted with distilled water;
- some small interruptions should be left
in the sealing to allow subsequent final injections when proper
maturing time has elapsed;
- as soon as the intervention is
completed, the area should be protected from rain water with
water-repellent treatment (see next paragraphs);
materials
to be used and quantification:
Materials to be used for
the intervention should be worked out trough laboratory tests in order to
determine the proper chemical contents and proportions depending on the
stones, (Tenelija or natural conglomerate), on the mortars originally
used, and on the technical requirements that are foreseen for the work.
The worked out products to be used should be tested on small portions
before the work is performed extensively on the damaged areas. Approval of
tests should wait the time necessary for the products to be matured, and
will depend on final result, appearance, colour, grains and efficiency.
Quantification and
proportions of the products used may be subjected to on-site modifications
depending on test results.
3.18.7 Remedial works for disgregate stone surfaces
description:
Tenelija stone blocks, that
are characterised by surface degradation, may be re-aggregated only if
damages are so developed to present stone powder and surface
pulverisation. Maintenance and control of the other cases is required
during time to perform additional interventions that may be necessary due
to unforeseen development of deterioration. The intervention may be
performed, (for Tenelija stone), with proper products based on ethyl
silicate or similar ones depending on laboratory and on-site tests.
Recent repair works,
performed with concrete should be previously removed, and masonry layout
should be repaired using original construction materials. Underwater
portions of the abutments should be inquired wholly, looking for any
damage, during suitable season time in which the water level is low.
methodology:
- Climate should be verified before
starting of the works and temperature should be included between +5°
C and +35° C;
- involved stone surfaces should be
perfectly dry, the atmosphere relative humidity should not be higher
than 70%, with no wind, smokes, and pollution vapours;
- adjacent surfaces, (not involved),
should be protected from the intervention;
- application may be performed after the
surface is cleaned, with the use of a paintbrush;
- the intervention should be performed
from top to bottom, uniformly and with no superposition;
- the chemical product should not dry
before the application is completed;
- paintbrush should be often cleaned;
- the involved surfaces should be
protected from rain water and humidity until the applied product is
matured and stable.
materials to be used and
quantification:
Materials to be used for
the intervention should be worked out trough laboratory tests in order to
determine the proper chemical contents and proportions depending on the
stones, (Tenelija or natural conglomerate), on the mortars originally
used, and on the technical requirements that are foreseen for the work.
The worked out products to be used should be tested on small portions
before the work is performed extensively on the damaged areas. Approval of
tests should wait the time necessary for the products to be matured, and
will depend on final result, appearance, colour, grains and efficiency.
Quantification and
proportions of the products used may be subjected to on-site modifications
depending on test results.
3.18.8 Remedial works for stone protection and waterprotection
According to LGA studies
and researches, it seems that, on the ancient stones, mysterious
"limewash or even adhesive layers" were present, and have been
defined by LGA "old enough to be ancient". This lead us to
hypothesised that ancient devices were applied on the stone surface in
order to protect the masonry from rain water, river and weather,
(according to LGA a sort of "linseed based limewash or similar for
protection"). Of course this is an extremely interesting matter that
absolutely requires further investigations before any protection
intervention is performed, also to avoid the loos of precious traces of
ancient refined construction techniques.
If the above hypothesis is
confirmed, it should be carefully evaluated if the ancient devices may be
adopted for protecting the stone surfaces, otherwise the following
procedure may be followed.
description:
Protection of surfaces,
(after all the other consolidations have been performed), by spray
application of a water-repellent and protective product. Quantification of
the product to be applied should be checked on-site. Surfaces to be
protected are the ones that are often underwater, mostly subjected to
damages due to river flows, and the ones that have been consolidated and
repaired.
The intervention may be
performed, (for Tenelija stone), with proper products based on
"alchil alcossi silani" or similar ones depending on laboratory
and on-site tests.
methodology:
- Climate should be verified before
starting of the works and temperature should be included between +5°
C and +35° C;
- involved stone surfaces should be
perfectly dry, the atmosphere relative humidity should not be higher
than 70%, with no wind, smokes, and pollution vapours;
- adjacent surfaces, (not involved),
should be protected from the intervention;
- application may be performed after the
surface is cleaned, with the use of a paintbrush;
- the intervention should be performed
from top to bottom, uniformly and with no superposition;
- the chemical product should not dry
before the application is completed;
- paintbrush should be often cleaned;
- any eventual excess of product should be
removed with the proper solvent (as defined by laboratory tests);
- the involved surfaces should be
protected from rain water and humidity until the applied product is
matured and stable.
materials
to be used and quantification:
Materials to be used for
the intervention should be worked out trough laboratory tests in order to
determine the proper chemical contents and proportions depending on the
stones, (Tenelija or natural conglomerate), on the mortars originally
used, and on the technical requirements that are foreseen for the work.
The worked out products to be used should be tested on small portions
before the work is performed extensively on the damaged areas. Approval of
tests should wait the time necessary for the products to be matured, and
will depend on final result, appearance, colour, grains and efficiency.
Quantification and
proportions of the products used may be subjected to on-site modifications
depending on test results.
3.19
Final works
Reference: |
BoQ |
6.0.0.0 |
Drw |
DS-01 |
After works for the
reconstruction of the bridge are over:
- a loading test should be performed to
test the structure;
- existing gangway (footbridge) should be
dismantled with related reinforced concrete foundation plinths and tie
rods;
- existing platform for ancient stones
storing should be dismantled with related reinforced concrete
foundation plinths; (not quantified in this drawing);
- all the provisional structures,
scaffoldings, centering plinths and any other element used for the
yard purpose should be removed;
- working area should be cleaned and left
in a decent appearance with no trace of the yard and of the stored
construction materials;
- any concrete and reinforced concrete
element should be removed even if located underwater and not visible.
Nothing should be
discharged in the river during the works and no polluting chemical product
should be used for the works. Lead should be used with high care, being
extremely toxic, and no fragment or small portion of it should be
discharged neither in the river nor in the adjacent areas.
3.20 Safety of workers and of the yard
The yard is foreseen to be
quite dangerous for the machinery to be used, for the site limited
accessibility, for the huge scaffoldings, for the river and for the
peculiar works that are planned.
It is strongly advisable to
work out a safety plan for the workers and for the yard, according to the
most recent international standards to avoid on site accidents.
General Engineering is not anyway and
anyhow responsible of any safety requirements and of any on-site accident.
|