3.6 Dismantling of the bridge remnants
Reference: |
BoQ |
3.1.0.0 |
Drw |
DS-01 |
Everyone would have liked
that this work stage weren't necessary, proceeding to rebuild over the
bridge remaining portions. But for many reasons, (explained in chapter 4,
§4.4 of this report), this seems to be technically not possible and a
portion of the ruins will have to be dismantled. Of course for the stone
elements of the bridge, which are still not fractured and in good
condition, it is required a dismantling with survey, numbering, storage
and remounting in the original locations.
Exact quantification of
dismantling is not possible without checks on-site during the excavation
works, therefore, different hypothetical excavation profiles have been
worked out, while, evaluation for the bill of quantities has been the
highest, in order not to need any review of the contractual terms.
Of course any technical
device, any on-site check, any possibility of reducing the dismantling
works, (due to the finding of good masonry that can bear loads), is
desirable and should be carefully investigated. At the same time it is
necessary to be well aware of the risk that is taken by loading released
masonry: if the new portions of the bridge lay on unstable layers,
structural cracks would develop and a collapse may happen as well. For the
above reason the work Supervisor will have the responsibility of deciding
whether it is possible to reduce dismantling or not.
3.6.1 Stabilisation of the cantilevering portions
Reference: |
BoQ |
2.0.5.0 |
Drw |
XXXX |
As it has been already
underlined, in order to avoid any collapse and in order to dismantle the
foreseen portions of the remaining parts of the arch, it is necessary to
design and fix provisional structures that may ensure the stability of the
cantilevering stones and may allow their dismantling in complete safety.
Moreover scaffoldings will be necessary either to perform excavations,
either to perform strengthening works: temporary structures should
guarantee a good accessibility of workers to the spot and the positioning
of small working machinery.
3.6.2 Repair works of structural cracks of the abutment walls
Reference: |
BoQ |
4.1.0.0 |
Drw |
PH-01; DS-01; RM-02;
RM-03 |
Before any excavation or
dismantling may take place, it is absolutely necessary to make sure that
abutment walls, which are bordering the bridge springers and which
contained the bridge thrusts, should be repaired. It is necessary that at
least structural cracks, detached masonry portions and leaning outwards
walls are repaired with tie rods.
Design for structural
repairs of the abutment walls has been worked out by CONEX Company on
their responsibility, as foreseen by assignments. General Engineering,
(not responsible for that type of works), simply would like to suggest to
use different strengthening devices from the one proposed: instead of
using anchor bars it would be better to use tie rods for their better
efficiency with released masonry. Anyhow it is absolutely important that
CONEX may have the possibility of reviewing the design for the abutment
walls being informed of the dismantling works which have been worked out
by current design, since CONEX was not aware of the excavations that would
have been necessary. A co-ordination of this peculiar matter is required
by PCU-TA.
The above mentioned repair
works are absolutely necessary to avoid collapse of abutment walls during
the dismantling; of course the works on the walls will not be finalised
and completed with all the non-structural repairs, because the dismantling
intervention is most likely to cause some settlings and some surface
damages. Finalisation of the repair works of the abutment walls may take
place after excavation works and bridge have been completed: when all the
other abutment walls will be repaired.
3.6.3 Dismantling by numbering of the bridge stone pavement
Reference: |
BoQ |
3.1.2.0-5 |
Drw |
DS-01 |
Stone pavement should be
accurately dismantled only in the portions where excavation will have to
be performed. Dismantling should avoid any further damage to the bridge
stone flooring and it is required that stones are surveyed and numbered in
order to be remounted, (if not cracked), in their original locations. This
procedure should be guaranteed by storing stone flooring, tiles and rows,
in wooden boxes lying in the correct position one next to the others.
Storing of the mentioned pavement elements should be in a safe and dry
place.
Single damaged stones of
pavement, not repairable, should be dismantled with accuracy and care in
order not to ruin the adjacent stones and the underneath mortar layer
(which has a waterproofing function). These damaged stones are sometimes
in isolated locations (quantification is by estimation) and some others
are in drawn areas (see drawing DS-01). Remedial works should preserve or
repair mortar layer underneath.
Portions of the pavement
which are covered by rubbles should be cleaned before flooring remedial
works, and anyhow all the area should be cleaned to allow a detailed
evaluation of the damaged portions. Moreover all the joints of the
remaining portions of the pavement should be cleaned from any recent
sealing intervention (joints have been sealed with plastic materials).
Existing stone krecnjak
socles (east side) between bridge pavement and adjacent flooring should be
dismantled with accurate survey and numbering of all the elements. This
work is required in order to perform an efficient waterproofing layer and
connection among different types of paving and in order to manage the
adjacent flooring slope. Storage and transportation in a safe and dry
place will be performed. During the repair works, elements that are not
damaged will be remounted in the original locations. Any stone element
that may be not reused, due to the damages and cracks, will be transported
to the temporary storing place where all the recovered stones have been
collected.
3.6.4 Excavation of the abutment and ground stabilisation
Reference: |
BoQ |
3.1.9.0 |
Drw |
DS-01 |
Dismantling works of the
abutments is a very delicate intervention that should be held with high
care and expertise: more than dismantling we should define it as high
accuracy excavation works. As already described, in previous paragraph,
bridge pavement should be partially dismantled, first, following the
minimum configuration as possible. Dismantling should be performed
proceeding from the top of the abutment going downwards, by manual
excavation. Machinery may be used only with the approval of the work
Supervisor and on his responsibility being aware of the following:
- only small mechanical machinery may be
used (also because of scaffoldings resistance);
- no high vibration may be caused;
- mechanical excavation should be
controlled and may be alternated to manual excavation.
Dismantling works of the
abutment should be performed while strengthening the adjacent ground and
while doing provisional works to avoid collapse of the abutment walls.
Sheet piles may be placed to brace the ground, as well as tie rods may be
used to avoid collapse, as represented in schemes of drawing PH-01.
Dismantling works of the
abutment, even if over-quantified, should be performed following the
smallest configuration as possible. This should be evaluated on site
depending on the stability of the abutment and on the safety of the
workers. Works Supervisor will be responsible of the above choice.
Dismantling works of the
abutment and of the bridge fill have been represented and quantified.
Three different configurations have been hypothesised: the smallest one is
the most desirable and the widest is the one that has been used for
quantification. Dismantling should be performed until a good and coherent
masonry layout is reached. All rubble should be removed as well as
unstable elements.
Works Supervisor will be
responsible either of the dismantling level to be reached, either for
dismantling line configuration. Dismantling limit should be, anyhow,
stair-shaped in order to guarantee a more efficient connection surface.
During dismantling works of
the abutment special care should be put to the room which is located
inside the east abutment in order that no inner structural damage takes
place.
3.6.5 Dismantling by numbering of the bridge stone elements
Reference: |
BoQ |
3.1.3.0 - 3.1.8.0 |
Drw |
DS-01; DS-02; DS-03 |
Remaining portions of the
bridge, (spandrel, cornices and parapets), will be dismantled with
accurate survey and numbering of all the elements. Special care should be
put during dismantling works of stones and of metal stuff, in order not to
provoke any damage. Storage and transportation in a safe and dry place
will be performed. During the reconstruction works, elements that are not
damaged, (to be decided on supervisor responsibility), will be remounted
in the original locations. Quantification of dismantling includes all the
remaining portions of the former bridge; remounting is equal to
dismantling and it is over-quantified since it will not be possible to
re-use all the elements.
Before proceeding to the
works some tests should be performed in order to find the best way of
disassembling metal cramps from the stones with no damage. Integrity of
stones that will be reused should be checked by ultrasound tests. Some of
the spandrel stones, (mostly the ones located on the north east side),
have high surface damages due to the shootings: repair of some of those
stones should be evaluated following similar techniques to the ones
proposed for the tenelija ashlars of the abutment walls.
Even krecnjak stone slabs,
which are over the lightening voids, should undergo to the same
dismantling procedures as the other elevation stone elements.
3.6.6
Dismantling of voussoirs: integrity limit
Reference: |
BoQ |
3.1.7.0 |
Drw |
DS-01; DS-02; DS-03 |
Structurally speaking, the
issue about the arch voussoirs to be left on-site is even more undertaking
than the previous one. During the first stages of the work many studies
and hypothesis have been worked out about the matter: for more notes refer
to chapter 4, §4.4 of current report.
Load bearing arch should be
perfectly integer and should guarantee a full performance with no
mechanical difference with all the other arch voussoirs: if the above may
be not fully demonstrated, those stone will have to be dismantled until
the arch springers, (following the highest level of proposed dismantling
profiles).
Final design has
preliminary proposed, (see drawings DS-02 and DS-03), an integrity limit
which has been worked out from investigation results carried by CONEX
Company. Only voussoirs, that had acceptable ultrasound test values, have
been included below the integrity limit, and those are the ones that may
be left on-site. But this may be worked out only after ultrasound test is
performed with ultrasonic instrumentation from intrados to extrados side,
(this way results will be much more reliable), and depending on the work
Supervisor responsibility.
Arch voussoirs should be
numbered and surveyed before dismantling; dismantling works should be
performed with special care to avoid damages.
3.6.7 Demolition of existing concrete blocks
Reference: |
BoQ |
3.1.1.0 |
Drw |
DS-01 |
Existing concrete blocks
should be demolished; those which are over the pavement should be
demolished before pavement remedial works; the others may be demolished at
the end of the works, once they are not necessary for any provisional
work. Demolishing of reinforced concrete blocks should be performed with
no vibration and taking care for the adjacent unstable structures.
Underground thickness of the blocks has been estimated and quantified,
(about 70 centimetres, as communicated by PCU TA). Demolition of
underground portions may be not performed if there is any structural risk:
to be decided on the Supervisor responsibility.
During demolition of
concrete blocks, special care should be reserved to the ones which are
located over the abutments void (room): it is most likely that the ceiling
of the void has been overloaded by the blocks and a collapse may take
place during the works.
Moreover, there is only one
case of demolition of a small masonry wall that is almost completely
ruined: it is located at the borders of the works limit by the north-east
side (drawing DS-01 position E-10). It should be partially demolished
until a good layer is found.
3.7 Centering erection
Reference: |
BoQ |
2.0.3.0 |
Drw |
XXXX |
As already mentioned,
centering erection should be performed during the right season time,
(refer to chapter 6), and once centering foundations are matured. General
Engineering is not in charge of centering design, and therefore no
specifications will be given, but some warnings about the matter have been
given in chapter 8 of this report.
General Engineering
suggests that centering foundations, centering itself and wooden deck
should be designed by one single Company or at least with a tight
co-ordination by PCU-TA, being all those structures quite connected.
Company that is in charge of the rehabilitation works will have to foresee
a lifting system powerful enough to bring and place the centering on site.
Centering may be composed,
(as it has been proposed in Construction Phases schemes), by five arches,
(with three hinges), at a distance of about 80-100 centimetres; load
bearing beam arches may be identically shaped with a regular profile
smaller than the bridge intrados arch.
3.7.1 Hydraulic jacks
Reference: |
BoQ |
2.0.4.0 |
Drw |
XXXX |
Centerings may have, at the
arch impost level, hydraulic jacks to allow adjustment and releasing when
it is required. These devices could allow the following curvature
adjustments:
- during first placement of load bearing
centering on-site
- when wooden deck is placed on-site
- in case of any slight settlement due to
dead loads
- for centering releasing
Company that is in charge
of the rehabilitation works should provide assistance to jacks maintenance
and regulation to gain the required adjusting.
3.7.2 Wooden deck placement
Following specifications
given for the stone final cut, (SC-final) in chapter 7 of this report, and
following additional specifications given in chapter 8 of this report, a
wooden deck is foreseen in order to obtain the irregular arch shape of the
former bridge. This wooden deck should be designed in order that it is
resistant enough to bear the load of the arch voussoirs, and should be
placed over the load bearing centering. Wooden deck will be, most
probably, composed by different sectors that could be re-assembled and
well connected once fixed over the arch false-work.
After wooden deck is
placed, small adjustments will be performed either with the load bearing
centering hydraulic jacks, either by settling the wooden deck itself:
adjustments will be defined by a permanent survey system of the reference
points located on the wooden deck.
Special care should be put
when the deck is positioned next to arch springers, due to the scarce
workability caused by the narrow spot. Deck should be placed over the
centering making sure that its intrados curvature matches perfectly the
load bearing centering profile: if this is not respected, unforeseen
discontinuities will be caused on the bridge arch intrados.
3.7.3 Control of the geometry
Reference: |
BoQ |
3.3.2.0 |
Drw |
RF-03; RF-04 |
Geometry control is
required to allow the performing of the bridge shape and mostly to check
the bridge intrados curvature. First geometry control is foreseen to
adjust load bearing centering following the specifications given in the
design of the arch false-work, and subsequently, to adjust the wooden deck
over the centering. The above task may be performed trough the survey of
reference points located on the temporary structures: those points may be
surveyed determining all the 3d co-ordinates with a professional survey
instrumentation, (electronic total station), that can have some base marks
unmoveable and linked to the ground. Survey instrumentation may be, this
way, replaced at any time in the same spot and periodical checks will
allow the correct proceeding of the works.
Geometry control should be
repeated while works are ongoing and at least every five rows of voussoirs
are assembled per each side. Co-ordinates survey should be constantly
compared with design drawings and data: reconstruction works should be
supervised with the help of these verifies in order to manage their
progression and their developing.
If geometry control is not
constantly and frequently performed it will be extremely difficult to
correct or recover any mismatching. Even if the bridge curvature is
supposed to be the most delicate shape to be repeated, also other bridge
elements like spandrels, cornices and parapets should undergo to these
type of controls to avoid remarkable differences among new bridge and
former one worked out trough the ancient survey studies and researches. Of
course temporary structures for the bridge construction should be designed
and built following co-ordinate data (refer to chapter 8 of this report
for more notes). The performing of this task is necessary to respect the
main objective of the assignment and therefore may be not neglected.
|