3.4 Design technical report: introduction
Here next it has been
reported about the foreseen design works giving a general description and
some technical specifications, warnings and requirements. A strict
connection with the bill of quantities (BoQ) and with the final design
drawings (Drw), has been carried on for a better understanding of the
different interventions and for a better explanation of the design
contents. It is suggested to read the following paragraphs having as
reference either the drawings either the bill of quantities.
As preliminary introduction, the site has
been described with notes concerning the current situation of the involved
architectural elements.
3.4.1 Current condition analysis: site description
Reference: |
BoQ |
XXXX |
Drw |
CU-01; CU-04; CU-05 |
The site where former
bridge was located is characterised by a scarce accessibility trough
ancient and narrow streets: (ulica Kujundziluk and ulica Oneskukova). The
bridge remnants are reduced to small portions and only few voussoirs are
still on site with some spandrel elements and some cornices. The bridge
look as if it were cut at the arch reins (east) and next to the abutment
(west): fill has been subjected to rain water infiltration which may have
ruined inner portions. Masonry due to the lacking of the bridge thrust has
probably released. Bridge ruins are in a precarious situation, (east side
more than west) and cantilevering over the Neretva; for what concern walls
of adjacent buildings, collapse is most likely to happen if remedial works
are performed over the abutments, (see building located south-east and
facing the river). (A co-ordination with the yard for the rehabilitation
of the towers is required in order to strengthen building walls and
adjacent structures before beginning of works).
In the abutment located
north-east, an huge void has been found and surveyed; this void is so wide
that partially interferes with the bridge thrust bearing masonry, and may
be reached during the dismantling works next to the springers. That void
may also be an impediment during the settling of flooring adjacent to the
bridge paving (which is over mentioned room).
The Neretva river may be
considered an impediment to the performing of the works, since the stream
is vehement and the flow changes quite frequently and quickly during
daytime. It is quite unlikely that any structure may be anchored to the
river bed, also because this would easily lead to dangerous consequences
in case of river floods.
All the area nearby the
bridge is in a state of complete abandonment since the war period (for
almost ten years): buildings, floorings, walls and finishing are ruining
and many concrete plinths for provisional structures have been placed all
over the area damaging the left portions of the bridge pavement which
prosecutes, (few metres), outwards on the two opposite banks.
Some more plinths and tie
cables have been placed by the north side, working as foundation
structures of a gangway which actually is located eight metres north and
parallel to the former bridge axe. All the above may constitute also a
limit to the installation and settling of the bridge yard, and this is why
no portion of that area has been proposed in the site organisation
drawings, where settling is foreseen to be fixed by the south side.
Some small pavement areas
are covered by rubble and ruined masonry, vegetation has grown but not in
a remarkable way except for some special cases on the abutment walls where
branches are coming out and damaging the masonry layout.
Stone elements of the
bridge, which fell into the river water, due to the shootings, have been
recovered after about five years of permanence on the river bed. These
stones of former bridge have been stored on a platform located
approximately 50-60 metres south-west to the bridge original location,
their quantity is 36% of the load bearing arch and 16% of the bridge
elements, their condition is quite variable. Traces of bevelling and of
fractures are present either due to the shootings, either due to the
destruction event and consequent falling from high level. Metal cramps and
dowels conservation is again quite variable but, considering the period of
permanence in the water, are not so much rusted. Two huge blocks of
assembled voussoirs have been left by the shore being too heavy to be
moved away for the currently available crane, and they still are subjected
to the river waters and to high deterioration.
3.4.2 Current condition analysis: abutment materials and pathologies
Reference: |
BoQ |
XXXX |
Drw |
CU-02; CU-03; CU-06;
CU-07 |
Abutment walls are
currently heavily damaged by shootings and they have structural and
superficial cracks, some of which developed before war events. Most
injured walls are located on the north east side, where shootings have
caused wide masonry lacks, (one of which is currently used as access to
the inner void); surface is highly deteriorated in many spots. Most
remarkable structural crack is located on the north west abutment and wall
is partially leaning outwards, while other walls, located on the south
side, are apparently in better condition and with isolated damages.
Ordinary traces of
deterioration due to the ageing are present all over the walls, as well as
stains due to the rich vegetation growing. Now that most of the green has
removed, (during investigation drilling works), traces of different
ancient repair works are visible and recognisable because of masonry
layout discontinuities.
Slight leaning outwards of
the abutment walls may have been recently caused also by the scarce
protection to rain water infiltration which can get inside the ground from
the top and from the ruining portions of the bridge.
Abutments may be mainly
divided in two different types: one lower portion which is characterised
by being built in Tenelija ashlars, and an higher portion which is built
in natural conglomerate masonry. Connection between the different types is
marked by a Tenelija cornice which is the direct prosecution of the bridge
cornice at the springer level. Tenelija ashlars are present also in the
upper masonry portions as strengthening devices at the corners. Top edges
of masonry abutment walls were covered by grey Tenelija sills which seem
to be a recent protection. Of the above mentioned sills only small
portions are left on-site. A small lower portion of the abutment walls is
built with Marl stone (south west).
3.5 General: preliminary workstage
Some preliminary operations
should be performed before any rehabilitation work could start, here next
are commented and briefly described. These works have been divided in two
categories:
- works that should have been already
performed
- works that should be preliminary
performed
The first group of works
includes also interventions in which General Engineering is absolutely not
involved, and for which no specification and advice will be given. In this
report, only for completeness sake, procedures will be mentioned: no
constraint and no impediments should be attributed to this simple list of
work stages, the aim of which is only to point out that these works have
been foreseen by PCU and PCU TA and that General Engineering has been
assured of that.
3.5.1 Works that should have been already performed
Refer to chapter six of
this report for more details about the work construction phases, even for
what concern stages not included in current design work (only generally
mentioned).
BoQ: XXXX
– foundation strengthening
Of course one of the work,
that should have been completed long before, (enough to have it matured),
is the strengthening of the foundations and their protection from erosion.
As far as it has been communicated to General Engineering by PCU TA, these
works should be performed until the bridge arch impost (springer) level,
and they are supposed to guarantee a foreseen maximum settling under load
action, given by General Engineering structural design (as defined by
Prof. Vignoli).
Also foundation for the
load bearing centering should be fixed on site in strict co-ordination
with the Company that will be in charge of the centering design. General
Engineering is not anyhow involved in any foundation work and for that no
design and no specifications are provided; nevertheless following notes
are given as a reference (but should not considered as work constraint):
Works on foundations seem
to be necessary to face the critical conditions of the ground underneath
the abutments as it has been investigated by CONEX Company. For what it
concerns the structural design requirements it may be said the following:
- Abutments shouldn't be loaded without
making the necessary remedial works on the foundations, (and on the
abutments as well).
- As proposed by PCU TA, the settling at
the springer level shouldn’t be more than one centimetre.
- It is required that the abutments will
be loaded about 6 months after the completion of the foundations
strengthening, (to be confirmed by foundations design). This way, the
possible settlings will happen gradually and will only be due to the
loads and not to the maturing of the repair works.
- The analysis on the results coming from
drillings will determine which is the best intervention for the
stability and resistance of the foundations, anyhow it seems likely
that it will be necessary to operate trough special concrete injection
to fill some caves. In any case it is required the control and the
limiting of the total amount of injected concrete and of any other
additional load to avoid settlings of the deep layers of the ground
that would be of future difficult management.
- From on site surveys and from CONEX
Company investigations it seems that the erosion phenomena is intense,
therefore the strengthening of the current situation may be not
enough: the erosion phenomena should be limited to avoid any future
problem to the foundations.
- The erosion phenomena, because of the
wide excursion of water level of the river, should be better achieved
not with concrete protections but with naturalist engineering systems.
BoQ:
2.0.3.0 – load bearing centering
Arch false work
(centering), presumably steel made, should be fixed and transported in a
safe place close to the work site. See chapter eight of this report for
more notes about this matter.
General Engineering is not
anyhow involved in any centering design.
BoQ:
2.0.2.0 – wooden deck
Wooden decks, either for
stone final cut, either to be put over the load bearing centering should
be completed. See chapter seven and eight of this report for more notes
about this matter.
General Engineering is not
anyhow involved in any wooden deck design.
BoQ: XXXX
– stone rough cut
Stone rough cut (SC-rough)
should be completed in order that stone blocks with quarrying tolerance
are all available and transported in a safe place close to the site.
Ultrasound check of their integrity should have been performed in order
that non inner fracture is present. See chapter seven of this report for
more notes about this matter.
BoQ:
3.2.0.0 – stone final cut of the voussoir
Arch voussoirs should be
already cut, (final cut - SC-final), on the wooden deck in order that they
are ready for a quick and accurate assembling. Ultrasound check of their
integrity should have been performed in order that non inner fracture is
present. See chapter seven of this report for more notes about this
matter.
3.5.2 Works that should be preliminary performed
Reference:
|
BoQ
|
1.0.0.0
|
Drw
|
general drawings
|
BoQ:
1.0.2.0 – work plan
A program of the works
should be proposed by the Company that will be in charge of the
rehabilitation works, in order to respect season times (see chapter six of
this report).
BoQ:
1.0.2.0 – construction drawings
Drawings of the yard
settlings and of any foreseen provisional scaffolding will have to be
prepared, mostly referring to the ones which have a structural function or
have to bear the load of machinery.
BoQ:
1.0.3.0 – topographic survey
A topographic survey should
be held, (by Company in charge of the works), in order to verify and
confirm the position of the arch springer levels and of the pedestrian
flooring levels, being those co-ordinates related to the coherence of all
the design, (matching of new interventions with the still existing
portions of the abutments). Co-ordinates should be communicated to General
Engineering and any eventual incoherence will be checked and analysed.
After this check is completed, the Company in charge of the rehabilitation
work will accept those measures and co-ordinates as reliable and will not
be allowed to complain about any incoherence pertaining matching of
ancient and new interventions in the bridge span.
BoQ:
1.0.4.0 – removal of blocks from the platform
Blocks of the platform
should be moved and stored to a temporary location that the City of Mostar
will provide in the meanwhile that a museum is settled. Temporary location
should be indoor or at least protected from rain water. Stones should be
moved with care avoiding any further damage or cracking due to
transportation.
BoQ:
1.0.5.0 – protection of assembled blocks on the river bank
Two huge blocks are
currently located on the river shore since they couldn’t be moved over
the platform due to their weight. General Engineering has suggested to
save those assembled blocks from quick deterioration and to move them in a
museum with all the other ancient bridge elements, (see starting
paragraphs of this chapter); while ICE has decided to leave them on the
shore as monuments of war events. If the ICE decision will not change,
those assembled blocks will have to be protected to avoid any damages due
to the yard ongoing works.
BoQ:
1.0.6.0 – monitoring
Monitoring of micro-shifts
of the abutment walls is required to allow structural controls of the
monumental complex before, during and after rehabilitation works.
Monitoring will allow also checks during time with season changing.
Monitoring sensors are required also during the bridge construction to be
inserted in the inner structural sections with remote control. A design of
monitoring is required with location and type of sensors for the abutment
walls, for any structural crack and for the bridge inner portions. In the
bridge inner portions sensors to monitor water infiltration should be
provided as well. After sensors have been installed it is required a
periodical and frequent check of the output results with related
structural interpretations given on written reports. When works will be
over, a control cabin should be fixed in one of the adjacent buildings so
that it will be possible to locate the instruments for saving the outputs
coming by remote sensors.
In detail, as guideline,
following control devices may be installed to have a complete monitoring
of the structure:
- rock meters (extension-meter bars) to
check any displacement due to the bridge thrusts;
- inclinometers to check leaning outwards
of the abutment walls;
- optical instruments to check any
displacement of key level, arch reins and arch springers;
- thermal sensors to check inner
structural variation;
- dynamic control sensors: one on the
bridge at the key stone level, and another one on a stable reference
spot.
BoQ:
1.0.7.0 – quality compliance control
Before the beginning of the
works a test for the Company in charge of the rehabilitation works is
required: some works should be performed in 1:1 scale with final finishing
and layout on some samples or models. Required tests are the following:
- assembling of a small portion of the
load bearing arch with front face finishing work;
- assembling of a cornice with parapet
with related finishing work;
- assembling of a spandrel small portion
with related finishing work;
- injection of masonry;
- repair of masonry and ashlar walls;
Results of the above tests
should be approved by the ICE and by UNESCO, and after approval they will
be taken as model for the on-site works. If tests are not approved, the
Company should be rejected from the performing of the works.
Once the parapet and
related cornice have been correctly assembled finished and approved, an
additional test is required to have some data for the structural design
which could not be gathered from scaled laboratory tests. The parapets
should be loaded with an horizontal thrust at an height of about cm 120,
(see structural design requirements), until failure of the 1:1 sample is
reached. Failure thrust has to be determined and communicated to General
Engineering in order to work out if any additional strengthening devices
is required to match current standards of safety for the people.
BoQ:
1.0.8.0 – public information
PCU and PCU TA will give
specifications and requirements for this peculiar item. General
Engineering suggests about this matter the following:
- to inform public long before works
begins in order to receive and use any observation;
- to be clear about design objectives and
contents.
BoQ:
2.0.5.0 – temporary stabilisation of the remaining part of the arch
In order to avoid any
collapse and in order to dismantle the foreseen portions of the remaining
parts of the arch, it is necessary to design and fix provisional
structures that may ensure the stability of the cantilevering stones and
may allow their dismantling in complete safety.
3.5.3 Site organisation
Reference:
|
BoQ
|
1.0.1.0
|
Drw
|
GE-03
|
Site organisation drawing
and report notes are mainly a guideline for a possible settling of the
yard: it should not be taken as a constraint, and any different settling
of the yard, that could optimise the performing of the works, may be
proposed and performed by the Company that is in charge for the
rehabilitation works of the bridge. Anything that concern the site
organisation has been defined by PCU TA trough sketches that have been
drawn in final layout by General Engineering.
Anyhow, limit of the yard
should be protected by fencing in order that access is reserved to workers
and supervisors only; moreover an access to the site by visitors, (e.g.
local authorities and press), should be guaranteed trough separated and
protected paths, (as it has been required by PCU TA). Gates should be
provided as well, to allow a secure closing of the yard during the non
working time.
Main access to the site for
workers, construction materials and for working machinery, may be the one
located south west by the main city road; this because works should not
interfere with another adjacent yard that will be ongoing for the
rehabilitation of the towers and annexed buildings. Only during final
stages, for the bridge rehabilitation works, it will be possible to get
trough the narrow streets leading to the bridge (Onescukova and
Kujundziluk streets), as required by PCU TA.
Position of the crane, and
related working range, may be considered only as a proposal, and should be
evaluated mostly by the Company in charge of the works depending also on
available facilities and on other technical evaluations.
General Engineering about
this matter underlines the fact that a crane of 60 metres operative range
may be not suitable for all the foreseen works, also because the
assembling phase of the voussoirs requires a more accurate lifting system
that do not have wide swinging. Concerning this matter, in design drawing
(GE-03), also another proposal has been showed in a sketch: a travelling
crane over lattice girders may run all over the area of the bridge length,
and a direct access to its base may be fixed (similar approaches have been
followed also in other bridge yards).
The yard might have its
headquarters and facilities on the west side of the main town road, while
all the other yard operative sectors may be located towards the river
shore on platforms high enough to avoid river waters.
Nevertheless all the above
mentioned hypothetical proposals should be technically verified for what
concern their feasibility and their efficiency, evaluating also that no
risk is taken due to the wild regime of river waters. General Engineering
is absolutely not responsible of any configuration of the settling of the
yard, of any provisional work and of any consequences due to river floods
over the site.
Another matter that should
be carefully evaluated, by the Company that is in charge of the
rehabilitation works, is that north to the bridge location there is a
footbridge that may be of impediment or constraint for the rehabilitation
works either of the bridge, either of the abutment walls: plinths and tie
cables have been placed by the north side, working as foundation
structures of the gangway which actually is located about 8 metres north
and parallel to the former bridge axe. For the above mentioned reason no
portion of that area has been proposed in the site organisation drawings,
where settling is foreseen to be only by the south side.
3.5.4 Site
limits
Reference:
|
BoQ
|
XXXX
|
Drw
|
GE-04
|
With the aim of giving a
clear limit that includes all the areas that should be rehabilitated, and
for bidding purposes, PCU TA has asked General Engineering to work out a
plan in which the limits of the interventions would have been marked. In
drawing GE-04 it has been represented the limit of the works with a bold
line. This line includes the areas that should be rehabilitated, and all
the abutment walls that should be repaired. Small areas next to doorsteps
of the entrances of other buildings should be planned and co-ordinated
with the design for the Towers (and adjacent buildings) since in some
spots stairs and steps may be restored. Limit line has not been drawn for
what concern the elevations since they are fully included in
rehabilitation works with no limit: from the rocks until the top.
It is included in the works
(even if not included by limit line):
- water drainage, waterproofing and piping
fixing as described in drawing AD-01
- stabilisation of adjacent bordering
walls and structures to avoid collapse
It is included in the works
(even if not included by limit line and to be performed after completion):
- existing gangway, (footbridge), should
be dismantled with related reinforced concrete foundation plinths and
tie rods;
- existing platform for ancient stones
storing should be dismantled with related reinforced concrete
foundations plinths;
- all the provisional structures,
scaffoldings, centering plinths and any other element used for the
yard purpose should be removed;
- working area should be cleaned and left
in a decent appearance with no trace of the yard and of the stored
construction materials.
|