3.3 Design objectives and
theoretical approach
Main design objective is to follow and respect the
request of the assignment that has been exposed in previous paragraph,
which has been always taken as reference direction during the performing
of the works, (providing required elaboration). At the same time,
coherently with the adopted approach, some additional indications,
concerning the philosophical contents of the design, have been developed
in order to gain a more mature awareness of the aims and finalities of
this delicate and peculiar rehabilitation intervention.
All the theoretical considerations that have been
developed have been exposed in the different stages reports, (Inception
Report and Phase A report), and given for approval to UNESCO and to the
ICE commissions (4th and 5th commissions).
In this type of intervention, and in this historical
moment, it is extremely important to define a correct and clear
theoretical approach to the design objectives, without which the whole
design would be fragile and would have to face frequent incoherences that
would invalidate also an operation perfectly correct on the technical
side.
3.3.1 Design
objectives description
This
Pilot Project has been named, in agreement with PCU TA, as "Rehabilitation of the Old
Bridge of Mostar" since it is partially composed by different practical approaches:
conservation and preservation, remedial and repair interventions, dismantling and
remounting operations and reconstruction works. All the above should be aimed at the final
rehabilitation and restoring of the Monumental Complex of the Stari Most (Old Bridge) of
Mostar.
Main design assumptions:
The recovered stones are, at the moment, the only
valuable elements of a great ancient monument, they have historical value, and they
represent an interesting example of the ancient technique of assembling voussoirs and a
constructive method which should be studied and investigated.
-
Some bridge stones and arch voussoirs have been recovered from the river and stored on a
platform. Recovered stones, which are apparently not broken and which original position
has been determined, are 9% of the global amount.
-
Some bridge stones and arch voussoirs are still built-in next to the former bridge
springers. Those built-in stones, which are apparently not broken, are 13% of the global
amount.
-
Abutment walls are, by now, damaged either by structural fractures, either by heavy and
light shootings, and by small surface degradations due to time.
-
Something, with the war, has been definitely lost and may be not recovered or restored.
Main design
interventions:
-
Recovered bridge stones and arch voussoirs, being what is left of the Old Bridge of
Mostar should not reused, but should be preserved exactly as they are and kept in good
condition to ensure their long lasting. This due either to restoration, either to
structural requirements (since the reuse would have caused a new stone cut and a
disassembling of the voussoirs).
-
Recovered bridge stones and arch voussoirs may be settled in a purpose built museum and
they may be organised for exhibition purposes. The original Old Bridge would be therefore
represented by those ruined portions, and this intervention would totally match the
International Principles of Restoration: it guarantees complete safeguarding and
preservation of the ruins and moreover it would be reversible and absolutely not invasive.
-
Recovered huge blocks of assembled voussoirs, that could not be settled on the platform
due to their weight, should be moved in a museum as well as all the other recovered
stones, to avoid their quick deterioration due to the river waters. (This despite ICE
wanted these blocks to be left as a monument by the shore).
-
On the spot where the bridge was, following the willing of the citizen of Mostar and for
social, political and symbolical reasons a "new old bridge" may be rebuilt as a
declared copy of the previous one. This copy should be built not approximately or just
close to the original one, since the value and the meaning of the new structure should be
in the "philological" and historical research of the ancient monument as if this
were an integration or a preliminary introduction to the visit of the real Old Bridge
settled in the museum.
-
Remaining built-in bridge stones and arch voussoirs, next to the springers and to the
abutments, should be partially dismantled, during the remedial works, and remounted in the
original locations, during the reconstruction works trough an anastilosis technique. This
dismantling has been required only to match structural and safety requirements.
-
Ancient abutments should be repaired only for what concern structural fractures and
heavy shootings: only for those damages that, due to the river floods, may lead to further
degradation if not repaired.
Rehabilitation
of the Old Bridge is therefore designed as a:
It has to be strongly underlined
that all the above listed items are only main design steps that represent, trough a
synthetic and simplified scheme, the objectives of the rehabilitation of the Old Bridge of
Mostar. Of course, either to gather a detailed explanation, either to understand which
have been the technical and theoretical reasons that have led to the above decisions, it
is necessary to refer to the subsequent paragraphs of this chapter, and to the whole
chapter 4 of this report.
3.3.2 Design
methodology
Design methodology has
followed mainly the ToR requirements, and has been developed considering
current approach criteria for similar type of rehabilitation
interventions. Design has been mainly structured in order to respect the
ancient remnants of the Old Bridge and the abutment walls and in order to
clearly declare which are the new interventions.
Methodology has referred,
moreover, to the requirements asked by the PCU TA, UNESCO and by the ICE
and has referred to the International Principles of restoration. In detail
we have:
-
Restoration should be performed trough
documented phases
-
Any integration should be documented and
recognisable.
-
For the strengthening aim of the
structure modern techniques may be used only for static reasons and
only when the ancient constructive method would not be adequate.
Design methodology has
referred, moreover, to the additional principles:
-
Preservation and special care should be
taken for the interior interventions, even if they are not visible.
-
Structure and technological solutions
should be maintained.
-
Interventions should be as less invasive
as possible.
-
Interventions should be as much
reversible as possible.
During the several stages
of on site surveys and design processing, it has been used exclusively
instrumental systems and computer systems. The procedures adopted
guarantee the following:
-
precise diagnostic and measurements
-
constant control and updating of the
designing stage
-
long-lasting, ready-to-hand and
duplicable data for records
For additional notes about
methodology refer to chapter 4 of this report.
3.3.3 Reconstruction
work methodology
It should
be underlined that the ancient Bridge of Mostar was built following a
methodology, a technique and a procedure which was typical of the ancient
times, linked to the available construction systems and machinery and
which, nowadays, may be only hypothesised. If a similar hypothetical
procedure were followed strictly, the final result would be the
construction of a similar Old Bridge: in other words, referring mostly to
stone layout and to curvature geometry, we would obtain a similar but
different structure.
For the
above reasons, coherently to the required objectives and aims of the
assignment, the design is not trying to re-perform all the hypothetical
steps of the ancient yard, (which in most cases happened to be randomly
performed, like the sorting of the stone sizes), but it has been found a
compromise among ancient methods and final results in order to gain a
structure identical to the former one even for what concern many details
like stone layout and geometry of the intrados curvatures.
The above
mentioned observations mostly concern the stone cut works, (refer to
chapter 7 of this report for additional notes), and the new technical
devices that will be used: like machinery and provisional structures.
Design objectives are,
therefore, aimed at reconstructing an "identical structure", (as
required), more than performing nowadays the same hypothetical yard
experience of the ancient time, which would be an interesting experience
but with remarkable different results and with technological and practical
difficulties. (Refer to §4.1.2 for additional notes).
3.3.4 Design
technological approach
Design has been developed
being well aware of the gap that there is among accuracy worked out in the
drawings and practical technical impediments and constraints in performing
the works on-site, having to manage the stone as construction material.
For the above reasons special devices and procedures have been worked out
in order that dimensioning of the different stones and voussoirs would not
be so difficult to be performed (refer also to chapter 7 of this report).
Moreover thank to the given
tolerances (like quarrying tolerances), and the management of some groups
of dimensions trough the range system, (refer also to next paragraph), it
will be possible to face this matter that has been defined as
"technological issue" of the design.
Geometrical and survey controls about the
proceeding of the works will be, for the above reasons, extremely
important and will have to be performed constantly while works are ongoing
to avoid any incoherence and unforeseeable result. (Refer to §4.1.2 for
additional notes).
3.3.5 Methodology
for determing ancient assembling criteria
Former bridge stone
elements were assembled with metal cramps and dowels sealed with lead
poured in purposely built slots. This refine technique has been
considered, in the design approach, as one of the most important value to
be preserved of the ancient construction: design has therefore studied
with detailed accuracy all the peculiarities and the positioning criteria
of the above mentioned metal stuff with the declared aim of gathering all
the wise devices that were proper of this ancient assembling method. At a
first glance, the positioning of the strengthening metal elements may seem
to be approximately performed, but with more accurate observations held on
the bridge remnants it gets clear that there were some important rules
linked to practical and technological requirements for the right
functioning of the structure. Before proceeding to final design, studies
and surveys have been performed, and for each element it has been
determined a range of location measurements and a range of dimensions. The
study has led to work out some limit measures to be respected in the
positioning of the metal strengthening devices compared to the shapes and
dimensions of the stone blocks and their joints. The same method has been
consequently applied to the stone blocks and to their carved channels and
slots.
Design dimensions and measurements, for the
above described devices, have been given with ranges and with limits
following the determined ancient criteria; this because it wouldn't have
been theoretically correct to give a single average dimension to be
repeated identically all over the structure, while, in the ancient bridge,
a different method was followed, which was more suitable to the
variability of the stone elements depending on the natural availability of
the quarry.
3.3.6 Management
of small irregularities
Former Bridge was
characterised by small irregularities, variations and by ordinary
constructive imperfections, of which there is no documentation, (apart
from surveys of the Bridge remnants). These small variations are precious
and are part of the beauty of the monument and shouldn’t be neglected to
guarantee the final global aspect of the bridge. In current design they
have been considered and analysed to fulfil to the required aim of
reproducing the ancient bridge as it was, and to avoid the construction of
a polished structure quite different from the former one. (See §4.2.3 for
additional notes). Design, in order to manage correctly the above
mentioned features, has given range dimensions for some of the elements
that were subjected to variations, (it wouldn’t have been correct to
assume an arbitrary measure for them all). At the same time, design has
adopted a tolerance systems which allows the possibility of slight
variations (in one centimetre range): leaving margins free to be slightly
managed during the on site stone assembling, by practical and manual
adjustments, similar to the ancient adopted techniques, this way we will
guarantee the reproducing of the same level of imperfections of the former
bridge. A special system of progressive control has been worked out to
make sure, step by step, that we are not going far from the final design
and far from the former bridge.
3.3.7 Management
of thickness dimensions
The ancient documentation
is poor of cross sections and of thickness and projecting dimensions of
the elements. This of course constitutes an important limit to the exact
global geometry determination, and these elements have of course a
remarkable esthetical architectural value. Inaccuracies in the geometry
determination of these dimensions may lead to a different global aspects
of the monument. (Refer also to §5.7 of this report).
For what concern thickness of spandrel,
cornice and parapet elements, dimensions, have been given by range values
being unknown and quite variable from the study of the bridge transversal
section. Design approach trough range dimensions for the undetermined
dimensions is one of the basic philosophical choice of this rehabilitation
design and it is aimed at reproducing the same quantity of randomly that
was proper of the former structure. Criteria adopted for range dimensions
are results of observations of the ancient bridge remaining portions.
(Refer also to §7.12.4 of this report).
3.3.8 Declaration
of new interventions
One of the most important conceptual risk
that we run by reconstructing the bridge, is to confuse the ancient
original elements of the abutments and of the bridge remnants with the new
interventions. This should not happen for a conceptual coherence, for
respect to the ancient left portions, and because history may be not
changed: with war, in fact, something has been lost forever and may be not
completely restored. The memory of what has happened should not be
cancelled and should leave at least a trace also on the Bridge. A refined
design plan with marking of some joints and stones, (see drawing AD-03),
has been worked out to gain the results with no-shocking devices but with
slightly interventions that at a first sight may be not gathered but with
an accurate observation they are readable. This marking of the joints and
of the stones is required for two different reasons: one is mainly
scientific, and related to restoration requirements for which it is
important to identify in future times each different intervention on the
monument; the other reason is instead historical, and is aimed at
preserving the trace and the course of time and events. (Refer also to
§4.5 of this report).
3.3.9 Use of
new technologies
New technologies will be
used for what concern working machinery and provisional structures like
centerings, scaffoldings and similar facilities for the yard purposes.
Not the same may be said
for the work phases: there will be different foreseen stages in which
traditional working and hand made working will have to be performed (like
all the finishing, stone final cut and assemblage of metal cramps and
dowels).
Construction materials will
be equal to the original ones unless structural and safety requirements
will impose the use of better performing materials. (This issue will be
finalised with the results coming from laboratory tests and consequent
structural design).
For the strengthening aim of the structure,
modern techniques may be used only for static reasons and only when the
ancient constructive method would not be adequate.
3.3.10 The
spirit of the works and design limits
No architectural design work will ever be
enough to guarantee a perfect result on-site for such a delicate
intervention as it is the rehabilitation of the Old Bridge of Mostar. To
gain an high level of architecture work, which could compete with the
marvellous former monument, all the given technical advises,
specifications, warnings and requirements will be useless if
rehabilitation is not performed with sensible, careful, humble and
respectful attitude. The quality results, final aspect of the structure,
architecture details, finishing works, are all in the hands of the Work
Supervisor and in the hands of the Workers: with equal technical
specifications we could have either the worst, either the best
intervention of the kind, depending mostly on the accuracy with which
works will be performed.
The spirit with which restoration works
should be held is not the same that is used for ordinary construction
interventions: money saving, serial organisation, simplifications, time
and deadlines are things which absolutely do not match with the
requirements of an intervention of this type. Rehabilitation should be
held with a spirit of research, of study, of understanding the ancient
values, of humble observation of the wise technique used many years ago.
If this spirit is not shared by all the members involved in the project,
then we will soon loose the real meaning of this work and we will get
something which will never satisfy the expectations of the whole cultural
World and, what is even worst, of Mostar citizens.
The rehabilitation of the Bridge will have
to be conceived also as an important moment for the population of Mostar
and of Bosnia: the symbol of the town will be restored after war events,
and the construction period will assume the characteristic of a local,
quite and thoughtful celebration, (not as a World press event).
Of course when works will be completed,
this project will soon lead to develop a cultural interest about the
monument and about the history of the town that should be valorised trough
the settling of a museum. This design work, among its main objectives,
foresees the foundation of a museum either to host the ancient ruins of
the Bridge, (plus studies and findings), either to host anything which is
related to the history of the town, which is still so little known and
spread out. In the museum, two blocks currently stored in Komos depot,
n°47 and n°48), could take place, as proposed by Mr Bessac, being traced
by carvings of ancient hand-quarrying-work that may has been performed for
the Old Bridge voussoirs.
Another matter that should be underlined is
about design limits. Limits lie in the fact that, in a restoration design,
it can not be possible to define everything at this stage, because it's
not possible to know everything about the site and about the ancient
ruins: trough investigations we do not get a complete knowledge like the
one during on-site excavations. For the above reasons it would not even be
correct to try to define and finalise anything concerning the works that
may lead to slight design changing and improving. Nevertheless design has
tried to give different options for matters that weren't still completely
clear.
|