PHASE 17-18

English english language


6.4.17 PH 17 - Pavement assembling and remounting 


  • Pavement mounting with care to connection joints among the flooring stones which should be close.

  • Remedial works to the remaining portions of the ancient pavement, and remounting of the pavement portions, (that have been dismantled with classification and numbering), in the original locations.

  • Pavement joint between new pavement and ancient one.


6.4.18 PH 18 - Fence fixing


  • Fence mounting in the same locations as the ancient ones and with same orientation and size.
  • Care should be taken in order to avoid damages to the parapets.


CREDITS:

Intellectual property of this report and of the design drawings is owned by General Engineering s.r.l.

author of the text: arch. Manfredo Romeo – other contributes have been mentioned in related paragraphs

© - General Engineering Workgroup -

SOURCE:

Final Design Report

back   back to menu
ani.gif (16635 bytes)
GENERAL ENGINEERING - P.zzale Donatello 4 - 50132 Firenze - Italy - ph. +39 055 2345256 - fax. +39 055 2476074