6.4.15 PH 15 - Upper cornice and parapets assembling 


  • Assembling of upper cornice and related parapets (finalisation towards the bridge center line).
  • Parapets should be carefully linked to the cornices.
  • Parapets due to their size and weight should be placed on site carefully and symmetrically in order to load correctly the bridge.
  • Fill should be prosecuted with finer grain size and a regular surface should be obtained.


6.4.16 PH 16 - Waterproofing and mortar layer


  • Waterproofing of the bridge is required with the use of a purpose mortar which will also be the bed for the flooring.


CREDITS:

Intellectual property of this report and of the design drawings is owned by General Engineering s.r.l.

author of the text: arch. Manfredo Romeo – other contributes have been mentioned in related paragraphs

© - General Engineering Workgroup -

SOURCE:

Final Design Report

back   back to menu
ani.gif (16635 bytes)
GENERAL ENGINEERING - P.zzale Donatello 4 - 50132 Firenze - Italy - ph. +39 055 2345256 - fax. +39 055 2476074