PHASE 07-08

English english language


6.4.7 PH 07 - Load bearing arch assembling 


  • Assembling of rows of voussoirs starting, strictly symmetrically, from both of the arch springers.
  • Starting stones at springer level should be adjacent to perfect masonry structure of the abutment.
  • Checks, by survey of control points, that shapes doesn’t change and no lowering take place.


6.4.8 PH 08 - Key stone placement


  • Assembling of key stone row.
  • Last row will not have any metal dowel.
  • Checks, by survey of control points, that shape hasn’t changed and no lowering has taken place.


CREDITS:

Intellectual property of this report and of the design drawings is owned by General Engineering s.r.l.

author of the text: arch. Manfredo Romeo – other contributes have been mentioned in related paragraphs

© - General Engineering Workgroup -

SOURCE:

Final Design Report