4.1 General
objectives
As specified in the
Inception report (see §1.1), in the Phase A report (see §1.1), and in
the previous chapter, here next it is confirmed the main purpose of this
assignment: the aim of this design work is to produce all the elaboration
required in the ToR following the listed purposes, among which, the most
important is to rebuild the bridge as it was before the destruction (see
§5.4.1 p.49 of ToR: "This section refers to the part of the
reconstruction or remedial works that will be carried out, and the result
of which should be a structure identical to the one prior to
destruction"). The mentioned design choice has been assumed as the
Client request and as Mostar citizen's wish for the future of the Old
Bridge with no further analysis and comments.
4.1.1
Additional objectives requirement
Of course, the above
mentioned main objective of the assignment, was not enough to complete
such a delicate task like the rehabilitation of a monument that doesn’t
exist anymore, and by the time that all the issues were analysed it got
self evident that a more detailed philosophical consideration was
required.
Since Phase A of the works
was ongoing, after a preliminary analysis of all the architectural and
structural issues concerning this task, it seemed that the Old Bridge of
Mostar was not a structure that could be recomposed by the use of its
ruins, or at least this could be done only for small portions and with
many difficulties of any kind: structural, architectural, practical,
historical, technical and conceptual (see the detailed analysis in this
report §4.3 §4.3.1 §4.3.2 §4.3.3). At the same time it has been
considered that the arbitrary "reconstruction" of a ruined
monument is not accepted by the International Principles of Restoration
which allow only interventions aimed at the "preservation" of
existing monuments and, only exceptionally, allow reassembling of small
portions of monuments trough the use of the anastilosis technique (if this
may be documented). For the aforesaid reasons the final objectives of the
whole project had to be taken into consideration to understand which could
be the real purposes of this plan, so that to have a guide during the
performing of the main design choices and in respect of the world
importance of the monument. A proposal aimed at a better clarification of
the finalities, that matched with the main declared objective of the
project, (to rebuild the Bridge as it was before destruction), and that
examined all the issues concerning this task, have been summarised as
follows.
The Bridge of Mostar has
been totally destroyed and doesn’t exist anymore as a whole structure,
its ruins are the only left portions of it and should be considered the
real and the only original Old Bridge of Mostar. The recovered stones are,
at the moment, the only valuable elements of a great ancient monument,
they have historical value, and they represent an interesting example of
the ancient technique of assembling voussoirs and a constructive method
which should be studied and investigated. These recovered stones being
what is left of the Old Bridge of Mostar should be preserved exactly as
they are and should be kept in good condition to ensure their long
lasting: they may be settled in a purpose built museum, (see also §1.4.5
of the Inception Report), and they may be organised for exhibition
purposes on a steel structure, similar to the bridge shape, on their
original positions. The original Old Bridge would be therefore represented
by those ruined portions, and this intervention would totally match the
International Principles of Restoration: it guarantees complete
safeguarding and preservation of the ruins and moreover it would be
reversible and absolutely not invasive. At the same time, on the spot
where the bridge was, following the willing of the citizen of Mostar and
for social, political and symbolical reasons a "new old bridge"
may be rebuilt as a declared copy of the previous one. This copy should be
built not approximately or just close to the original one, since the value
and the meaning of the new structure should be in the
"philological" and historical research of the ancient monument
as if this were an integration or a preliminary introduction to the visit
of the real Old Bridge settled in the museum. This way the project will be
at least more correct and clearer in its aims and in its results, and will
respect the ancient ruins and will allow any future different solution or
study.
For the above reasons one
of the main objective is to keep physically, (but not theoretically),
divided anything that concerns the ancient original structure from what
concerns the new "philological" reconstruction of it; moreover
another main objective of the work is represented by the importance of
rebuilding the new structure as much close as possible to the original
one, since a structure just alike to the ancient bridge would be
meaningless and would not even contribute to the ancient monument
documentation. During the performing of the design and of the works many
difficulties will arise due to these requirements of similarity but if
just once, to make it easier, we start performing things differently we
would soon loose the limits and our objective, because with the next
difficulty we will be much more authorised in making things not
identically to the original model since we are already far from the
ancient bridge and we may feel it is not worthy to devolve more efforts
towards that aim.
For more details about all
this matters and about the use of the ancient stones see §4.3 in this
report and specially §4.3.3.
4.1.2 Design
requirements and complexity
The reconstruction of the
"new Old Bridge" is not an easy task, and the thing that is more
important to point out is that the reconstruction works will not be
identical to the constructive methods used at the time for that bridge and
for any other ever built. Anything will be much more complex due to the
requirement of making all things identical, stone by stone, to the
previous one.
The Old Bridge of Mostar
was probably built following a design of the global shapes, sections, and
structures but the stones were put on site following average dimensions
and depending on the quarried blocks. In other words the quarried blocks
were of different sizes, and they were cut as voussoirs on site, making
them all alike for the face dimensions and using the different thickness
with few rules, making only sure that intrados joints were not on the same
position. As final result we have that each voussoir is different from the
others and that, being the north and south spans different, each arch row
changes its sizes in the bridge thickness. All these irregularities were,
on the ancient yard, absolutely caused by the working procedure, the
morphological characteristics of the site, the arch centering, the stone
cutting instruments, and by the original stone blocks as they were
quarried.
Nowadays, if we want to
rebuild a bridge identical to the previous one, we have to face, first of
all, a technological problem because on the design side it is possible to
control and determine each stone size, shape and position but on the stone
cut side it is not an easy task to perform the exact design indications.
Knowing all the 3d co-ordinates of the intrados and extrados curves, all
the dimensions, all the deviations from the plans, all the diagonals and
all the joint tolerances it is possible to give more then 200 dimensions
for each row but this dimensions would be useless for the stone cut
workers. It would be different if we were talking of steel but here we
have to manage stone: the design of the reconstruction of the Old Bridge
had therefore mainly a technological problem to face that has never been
faced.
General Engineering has
proceeded in facing the above mentioned limits and has worked out, [see
chapter 7 of this report], a new design system to allow the performing of
the exact stone cutting trough the use of simple and practical on site
methods. This way workers, without being even aware, will reproduce,
following some procedures and a little number of dimensions, the stone row
exact dimensions of the load bearing arch.
On the other side it is
important to respect and perform a control method at predefined steps: one
inaccuracy on one row may even be difficult to be surveyed but every five
or ten rows there should be reference points and control systems so that
to check the proceeding of the works.
This design for the bridge
reconstruction couldn't be easily represented only by plans, sections and
elevations, but it has been necessary to produce a sort of on-site manual
containing all the necessary assembling procedures to guarantee the exact
performing of the works.
4.1.3
Design principles and methodology
As specified even in the
Inception report (see §1.2), here next it is confirmed the methodology
that has been followed for the performing of this assignment: the design
has followed scientific methods, existing documentation and restoration
procedures; the design procedure has taken also into consideration any
evolution during the developing and the performing of the assignment: many
details have been discussed by the time they got self evident. For the
above reasons, and since the plan was quite complex and linked to many
investigation results, not all of the design choices could be specified in
advance, but only at this final stage; nevertheless still some matters
will have to be finalised while works are ongoing.
The methodology that has
been adopted for the design in each step is the following:
first to determine which
were the ideal architectural solutions of each matter and then to verify
them with all the technical parameters of resistance and feasibility.
Methodology has referred,
first of all, to the requirements asked by the PCU TA, by the ICE, by
UNESCO and, as much as possible, to the international principles of
restoration; for what concerns this assignment we have in detail:
- Restoration should be performed trough
documented phases
- Any integration should be documented and
recognisable.
- For the strengthening aim of the
structure modern techniques may be used only for static reasons and
only when the ancient constructive method would not be adequate.
Moreover methodology has
referred to the additional principles:
- Preservation and special care should be
taken for the interior interventions, even if they are not visible.
- Structure and technological solutions
should be maintained.
- Interventions should be as less invasive
as possible.
- Interventions should be as much
reversible as possible.
During the several stages
of on site surveys and design processing, it has been used exclusively
instrumental systems and computer systems. The procedures adopted
guarantee the following:
- precise diagnostic and measurements
- constant control and updating of the
designing stage
long-lasting, ready-to-hand and duplicable
data for records
|