7.1 Introduction to stone cut
procedures
The
stone cut final design is rather complex due to the main requirement for the
reconstruction of the Old Bridge which is to gain a structure identical to the one before
conflict events, as required by the City of Mostar. Being the bridge characterised by many
peculiarities and ordinary hand working construction imperfections, the stone cut is
somehow atypical and for this reason some requirements and specifications should be
pointed out.
The reconstruction work of the bridge will not be
similar to the procedure adopted at the time when it was first built (even if the result
should be the same): in the ancient times, in fact, stones were quarried and cut following
average measures and mostly depending on the quarry natural availability, stones were
assembled on to the centering almost randomly taking just care of a few rules (like stone
joints shift, global thickness of the load bearing arch, thickness of each row and row
parallelism). The bridge was therefore perfectly built but not regular, its anomalies due
to this regardless way of choosing the voussoirs were at the same time the real beauty of
the bridge and the origin of a complex geometry.
Today, knowing the most likely geometry of the bridge, and willing
to have the previous shape and same imperfections and locations we should follow a stone
cut design carried out stone by stone where each element will have a peculiar shape and a
planned position. A purpose built method and procedure has been worked out in order to
perform quite easily all the measures, but recommendations are necessary to follow
correctly all the design steps. General Engineering will not be responsible of any
incongruity if design recommendations and warnings are not strictly followed.
7.2 Methodology and theoretical
approach to stone cut
As
already mentioned in previous paragraph, main assumption of the current work is that
design should be aimed at the reconstruction of a structure identical to the former one,
and this in order to give to the new structure, (clearly declared as new), an additional
value of historical and scientific documentation of the ancient one (for other notes refer
to "main objectives" in current report).
The above assumption doesn't absolutely mean that it
is at the same time possible to follow the ancient constructive methodologies and
techniques to gain this objective: it has to be clearly underlined that we are not
repeating the same constructive experience that took place in the past, mostly because
this way it wouldn't be possible to respect fully the objective of the work, this even if
sometimes it is of great use to repeat some steps and to study and make researches on the
hypothetical methods followed at the time.
The stone cut of the arch voussoirs is one of the
works that may be not repeated following the ancient methods but following another
technique that may guarantee a geometrical final correspondence to the ancient structure.
The way this design of stone cut has been conceived and performed wouldn't have been
possible without a computer management of all the data representing the 3d co-ordinates of
every single stone joint of the arch. Stone wasting optimisation, management of
irregularities, anomalies and documented imperfections concerning raising and heights of
rows have been planned trough the use of purpose built software calculation routines and
every single stone has been represented in 3d digital drawings and defined in its final
co-ordinates and dimensions: stone cut design has soon brought to manage an electronic
chart of many sheets with a global amount of elements that, including the analysis stage,
counts about 200.000 data.
Nevertheless beyond this exact method for geometry
control, it has been carried out a special methodology to manage and repeat smaller
ordinary constructive imperfections trough special devices which will follow some
procedures and steps of the ancient way of assembling the arch but in predefined ranges
and to be performed among points of known positions.
Moreover anything which is concerned with the final finishing and
working of the surfaces is foreseen to be performed trough hand working and trough
detailed specifications and checks in order to control the bridge final appearance and its
esthetical value.
7.3 Stone cut warnings
Stone
cut design is divided in two main groups of measures: one is related to the quarrying
work, and the other is aimed at the final cut. Data are organised in four different books
subdivided in charts, schedules and sections that will be explained later in this text,
moreover drawings in 1:25 scale are provided. All the above is useless if it doesn't go
with the following main warnings and with all the instructions given in the current
chapter.
stone type for all
the bridge elements (SMS-A and SMS-B)
Stone to be used and cut is Tenelija of the same
type, colour and resistance of the ancient one originally used for the bridge
construction, quarried in the same quarry where the ancient stones where presumably
originally taken. Detail specification to guarantee the above requirements will be given
by LGA company (which is in charge of all the laboratory tests).
Stone quality and correct procedures for all the
quarrying phases should be guaranteed by a supervisor that is supposed to be on site
during the works and that has the necessary expertise to make the checks. The supervisor
should also check that the bedding is respected coherently to the warnings here next
reported and that the numbering is performed as well as here next explained.
For what concern the lowest required resistance to
compression stress and for the mechanical characteristic of the material it should be
referred to the structural design report.
integrity and
quality of the construction material
Each block of construction material should be
checked with ultrasound tests at least once, before installation, and if necessary, more
than once to establish the responsibility of the different involved companies; this will
be up to the PCU TA. Ultrasound checks should be performed with the presence of a
supervisor, and acceptable limits will be defined on the basis of the results of LGA
company (which is in charge of all the laboratory tests).
joint tolerance
(equal to zero)
Main assumption of this work is that all the
measures of all the stones of the bridge are worked out considering the joints equal to
zero. This assumption has been agreed with PCU TA and is aimed at a global simplification
of the work mainly in the management of the co-ordinates which are therefore referred to
the center line between two adjacent stones or voussoirs. Moreover this approach was
necessary since the average dimension of the joint was not yet defined, at the current
design stage, depending on many matters and being in the ancient construction quite
variable.
On the other side this choice has been found
favourable since joint dimensions will be used during the final cut as an additional
margin to be managed in the assemblage phase, coherently with the global design approach
which foresees this method for the sub-centimetre dimensions in order to perform a
randomly distributed amount of ordinary construction imperfections.
quarrying tolerance
(equal to cm 3)
Another assumption adopted for this work, agreed
with PCU TA as well, was to work out dimensions for the stone blocks to be quarried
increasing them of a quantity of three centimetres per side. Being the voussoirs of
irregular shapes, the above mentioned device wouldnt have guarantee a feasible
procedure for the quarrying work and for this reasons it has been provided an additional
calculation aimed at working out the smallest parallelepipeds dimensions as possible that
could contain each stone to be cut. In other words, trough a purpose built software
routine, three dimensions have been worked out for each stone block to be quarried,
representing the base, height and thickness of a parallelepiped that is big enough to
contain the final voussoir solid shape with a tolerance of a minimum of three additional
centimetres for each side. Note that "for each side" means that if a base
dimension is taken, for instance, this will be longer of a quantity of three centimetres
on the left and of three centimetres on the right which in total brings six centimetres
referred to that single measure.
To minimise the stone to be quarried these
parallelepipeds are calculated along the average center line of the thickness of the
voussoir to be cut and along the center line of the voussoir face, and this method will
lead to a slightly variation of the ideal orientation of the natural stone bedding;
mentioned variation is anyhow negligible.
stone natural
bedding
The terms "stone natural bedding" are
referred to a natural characteristic of the lime stones (like tenelija). Lime stone has an
orientation, (bedding), due to different layers that during time have settled forming the
stone vein, this natural orientation has an important structural value for stones used in
constructions: stress should be orthogonal to the natural bedding.
For the above reason attention should be put during
quarrying and during final cut in order to prepare stones with the correct orientation and
not up side down.
In detail, during quarrying, the parallelepipeds
should be taken out in a way that dimensions are compatible with the final assembling
position: this means that depending on the type of block (voussoir, spandrels, parapets
and cornices) a different approach should be followed as here next resumed (better
explained in following paragraphs and in reconstruction works drawings):
ELEMENT |
BEDDING |
PARALLEL SIDES |
voussoir
(arch stones) |
Bedding
parallel to: |
Hqt
dimension |
K(n)qt
dimension |
spandrels |
Bedding
parallel to: |
bqt
dimension |
t
dimension |
cornices |
Bedding
parallel to: |
bqt
dimension |
t
dimension |
parapets |
Bedding
parallel to: |
bqt
dimension |
hqt
dimension |
Immediately after the quarrying a
clear and undeletable tag (sign) should be stuck on the side of the stone which is
parallel to the stone bedding, this to avoid misunderstandings with the following phase of
final stone cutting (also because the bedding may be not clearly visible after stone
drying).
During stone final cut the care for the natural
stone bedding will be important as well, but it will be of help either the mentioned tag
(sign) either the dimensions of the quarried block.
numbering and coding
Numbering and coding of quarrying blocks is
essential, if this operation is not correctly performed the bridge may be not easily built
following the design indications. Immediately after the quarrying a clear and undeletable
tag (sign) should be stuck on the stone (may be together with the indication of the
bedding) with code and number that has been proposed in the classification system.
For instance signs like the following:
SMS-A103/5 means: arch stone located in row 103
position 5th (starting from north)
SMS-Bsp_ne79 means: bridge spandrel stone located on
the north-east side position 79 (ref. drw.)
Also after the stone final cut the tags (signs)
should be repeated on the stones to avoid position exchanging during the delicate phase of
the assembling.
stone final cut
Stone final cut should be performed following
strictly the specifications exposed in this chapter and in the one about the centering; as
it will be explained, final stone cut will be performed on a wooden structure model 1:1
identical to the one that will be settled on the load bearing steel centering.
Final stone cut will have to be performed with the
control of a supervisor that is totally informed of the architectural design results and
objectives and well aware of the warnings and instructions here reported. A 1:1 test
before the beginning of this work is required in order to obtain the approval of the ICE
commission.
Stone final cut should be performed following
architectural design, either for what concern the final geometry, either for what concern
the different steps and procedures of preparation: it should be completed off site on a
model wooden deck in order to be assembled and finalised in a short time and with no
incoherences. Any other different approach is most likely to be incompatible with the
planned dimensions either for the stone final cut, either for the stone rough cut, and may
lead to the following consequences:
- quite different geometry and final appearance of the bridge arch
- different number of rows and different shape of voussoirs
- incoherence and unmatched of joints (specially inner joints among
rows)
- rough stone blocks and final stone blocks may not be adequate or
enough dimensioned
- time for assembling may get too long and bring to the bad season with
high risk for the whole structure
General Engineering will not be responsible of any
of the above matters if design is not fully and strictly followed.
stone finishing
Stone finishing should follow specifications given
by Mr. Bessac (who is in charge of all the archaeological research as a stone expert). LGA
company findings about the different type of surface working should also be taken into
consideration for the mentioned purpose.
A supervisor with the expertise on stone working
should be present in order to check the correct performance of the required
specifications. A 1:1 test before the beginning of this work is required in order to
obtain the approval of the ICE commission.
involved stones in
stone cut design
The design of the stone cut involves all the bridge
stones, even those that are still built-in (SMS-BS) and those that have been recovered
(SMS-RS). As far as the arch is concerned, all the voussoirs have been designed from the
arch springer.
Stone cut design of all the stones has been
necessary and required for different reasons:
- recovered stones (SMS-RS) won't be reused to avoid additional cut of
ancient stones and to avoid repositioning in different locations;
- it is not possible to foresee, at this stage, how many of the
built-in stones (SMS-BS) will be remounted in the original locations (depending on
integrity and on disassembling);
- for what concern the load bearing arch, only built-in stones in
perfect conditions might be left on-site (to be decided while works are ongoing);
- for the reconstruction work some extra stones are required.
note
The delicate type of work and the amount of design
documentation and investigations produced requires a permanent presence of a supervisor
with the necessary expertise, in order to face any difficulty that may arise while works
are ongoing.
An additional 10% (35-40 cubic metres) of extra stone is desirable
since during the works some stones may be damaged by ordinary constructive procedures. |